Construction Updates

Post Date:01/02/2018

 Construction Updates


 

Project:               ***STARTING SOON***  WW17-0600 SS6 Theresa Avenue and Los Altos Drive  ***STARTING SOON*** 

Description:         The WW17-0600 project consists of replacement of an existing sewer line and laterals, storm drain improvements, construction of curb and gutter, grind, overlay and striping of the street. 

Location:              Los Altos from West side Rio Del Mar to Theresa Avenue and a portion of Theresa Avenue

Contact:              Mark Stinson 647-5315

Week of 1/22:     Pre-construction meeting

Week of 1/29:     Due to the nature of this project the road MAY be closed to non-residential traffic during work hours.  Signs will be posted. 


 

Project:                SR 29 / Napa Junction intersection 

Description:        The “Highway 29 at Napa Junction Road Intersection Phase 2 Project” (TR17-0200) consists of roadway and traffic signal improvements at the intersection of Highway 29 and Napa Junction Road.  It includes the addition of turn lanes on the east leg of the intersection and widening of curb returns at the NW, SE and NE corners.  As mentioned above, it also includes the unfinished City Public Improvements.

Location:             East side State Route 29 (Broadway) and Napa Junction Road

Contact:              Juan Trupp 707-571-8005, 408-417-6794

Week of 1/22:     Beginning Monday Night from 9 pm - 6 am shoulder work will be underway.  Shoulder work may require a single lane closure for the Safety of the Work Crew.  Please watch the signs for notifications and proceed through the area with caution.  Day work will also continue from 6 am - 5 pm no lane closures are anticipated for Day work.   


Project:               WA17-0400 W2 Annual Water Main Replacement - Capra Water Main Replacement

Description:        The WA17-0400 project will replace the Water Main on Capra from Danrose to Elliott.  The project will take 4-6 weeks.  During this project there will be trench plates in the roadway. 

Location:             Capra Drive between Danrose and Elliott

Week of 1/22:     One way traffic control will be effect during work hours.  Expect delays when traveling in this area.  Please watch for traffic changes in this area and travel through this area with caution.   

Contact:              Mark Stinson 647-5315


Project:               Valley View Senior Housing www.sahahomes.org/apply

 

Description:         Valley View will consist of 70 one and two bedroom units, for seniors aged 55 and over and Veterans.

Location:             Theresa Avenue between Eucalyptus Drive and Napa Junction Road

Contact:              Mark Stinson  707-647-5315

Week of 1/22:     Deliveries may require intermittent traffic control.  All work will be on site.  Please proceed thru the area with caution and watch for flaggers.


 Project:               Boys & Girls Club

Description:        The Boys & Girls Club will consist of a 14,984 sq ft building and will house multiple programs for the children of American Canyon including a Teen Center, Drop-in Center  and a community gathering space to name just a few of the amazing things to come.   

Location:             60 Benton Way at Donaldson

Contact:              Mark Stinson  707-647-5315

Week of 1/22:     The Sidewalk in front of the project will be closed during construction.  Traffic Control will occasionally be in effect and require the 2 lanes of traffic to be shifted to allow work on the shoulder of Benton Way.  Please proceed thru the area with caution.   


 Project:               Village at Vintage Ranch

Description:        The Village at Vintage Ranch is a 159 three-story townhome rental apartments among 17 residential buildings on 11.53 acres at the northwest corner of Silver Oak Trail and American Canyon Road. 

Location:             East side of SR29 between American Canyon Road and Silver Oak Trail

Contact:              Tom Donahoe, Ghillotti 707-556-9145

Week of 1/22:     Contractor will be working onsite 7 days a week.  Delivery of equipment and materials may cause brief delays on Silver Oak Trail. 


  Project:              PG&E Substation - Corner of American Canyon Road and Highway 29

Description:        Under contract, Coast Landscaping, will be planting new landscaping on the corner of Highway 29 and American Canyon Road near the PG&E substation. The "Welcome to American Canyon" sign will also be refreshed during this project.

Contact:              Brian Materne, Parks Supervisor, (707) 647-4591

Week of 1/22:     Topsoil amendments are being completed and weather permitting plants should be going in by the end of the week.


 Project:               Jim Oswalt Way

Description:        This project consists of building construction. 

Location:             Jim Oswalt Way from Green Island Road to end of street

Contact:              Dennis Chilton, Buzz Oates Construction 916-257-1881

Week of 1/22:     Traffic control will be in place during work hours on Jim Oswalt Way, expect brief delays.

 

Project:                 Green Island Road Reconstruction and Widening

Week of 11/20:     Exploratory work may delay traffic briefly on Saturday's only for the next few weeks.

Contact:                Ron Ranada, Senior Civil Engineer, (707) 647-4559

 


 

 

 