Construction Project Updates

Print
Press Enter to show all options, press Tab go to next option

Revised 9/7/18


Project:           SS4 Broadway-South of Crawford Way Project (WW18-0300) 

Description:
    This project consists of replacing an existing 10-inch sanitary sewer main with a new, larger 15-inch main.  Work will take place in the Right of Way behind the shoulder of Broadway (SR29) and the intersection of Crawford and Broadway (SR29).

Location:         3300 block of Broadway (SR29 at the Open Door Church) to Crawford Way.

Contact:           Patrick O'Connell, Devaney Engineering, 415-912-7227

Week of 9/10:  The Contractor will begin mobilization this week. There will be no traffic control in effect this week.  

 


 

Project:           Village at Vintage Ranch

Description:    
The Village at Vintage Ranch is a 159 three-story townhome rental apartments among 17 residential buildings on 11.53 acres at the northwest corner of Silver Oak Trail and American Canyon Road. 

Location:         East side of SR29 between American Canyon Road and Silver Oak Trail

Contact:           Tom Donahoe, Ghillotti 707-556-9145

Week of 9/10:  ****Pedestrian Detour****  The Sidewalk on the project side of Silver Oak Trail will be closed from Spinetta Court to American Canyon Road.  Please use the non-project side of Silver Oak Trail or Sequoia Grove Way and Toscana Drive as an alternate route to American Canyon Road.  
Contractor will continue working onsite Monday - Saturday.  Delivery of equipment and materials may cause brief delays on Silver Oak Trail. 

 


 

Project:            Valley View Senior Housing

Description:     Valley View will consist of 70 one and two bedroom units, for seniors aged 55 and over and Veterans.

Location:          Theresa Avenue between Eucalyptus Drive and Napa Junction Road

Contact:           Mark Stinson  707-647-5315

Week of 9/10:    Deliveries may require intermittent traffic control.  All work will be on site.  Please proceed thru the area with caution and watch for flaggers.  


 

Jim Oswalt Way

Description:     This project consists of building construction. 

Location:          Jim Oswalt Way from Green Island Road to end of street and East of 1300 Green Island Road for 1/4 mile.

Contact:           Dennis Chilton, Buzz Oates Construction 916-257-1881

Week of 9/10:  Single lane traffic will be in effect this week.  Right of Way work will be completed this week.  Contractor will be working on site. 


 
Project:  Sidewalk Installation - Donaldson Way between SR29 and Carolyn Drive
Anticipated Start Date - September 17, 2018

The project consists of new  sidewalk on the south side of Donaldson Way between SR29 and James Road and on the north side from James Road to Carolyn Drive.  This will provide a continuous path  from SR29 to the Middle School. In addition the City will be creating a Class III bike lane by installing shared roadway bicycle markings or  “sharrows” in Donaldson Way .  

For more information contact 647-4558.


Project:  Annual Pavement Management

The Annual Pavement Management program will Grind and Overlay 10 streets in American Canyon.  Staff anticipates the work will take approximately one month once it begins.  Based on the Pavement Condition Index (PCI) and the required subsurface utility work necessary in the City, the following streets were chosen to receive Grind and Overlay this Fall.   

Ascot Court
Bedford Lane
Brookshire Way
Capra Drive
Chaucer Court
Kent Way
Kingsly Lane
Knightsbridge Court
Knightsbridge Way (Danrose to Banbury)
Patricia Drive